Installation of DCS system

DCS system consists of hardware and software. Hardware installation of DCS system includes installation of panels, cabinets, machines and wiring between them, system working grounding, installation of power supply and basic control parts, safety grounding and isolation.

External conditions for DCS system installation

1. Control room and operation room should meet the use conditions:

Before installation, the civil engineering, installation, electrical and decoration projects of the control room and operation room must be completed, the interior decoration must meet the design requirements, the air conditioner must be enabled, and equipped with a vacuum cleaner;

The ambient temperature, humidity, lighting and air purification level must meet the operating conditions of the DCS system before unpacking and installation.

2. Requirements for installers:

Installers must keep clean and must wear clean special slippers when working in the control room or operation room to prevent dust from entering the DCS system device;

Try to avoid the influence of electrostatic induction on system components. During debugging, do not wear chemical fiber and other fabrics that are prone to static electricity. (Please refer to the issues often overlooked by automatic control engineers - static electricity & moisture-sensitive protection)

Transportation and installation of machines, cabinets and trays

Machines, cabinets and trays are required to be transported to the control room as a whole and unpacked before installation.

Care must be taken when transporting, unpacking and handling DCS system hardware packaging boxes to prevent tipping and strong vibration to avoid accidental losses.

When unpacking, personnel from the equipment supply department and personnel from the receiving, maintenance and inspection departments should be present to jointly check the appearance quality, defects in the wiring of the internal card parts of the equipment, documents and materials brought by the system, etc., and keep records and sign for confirmation.

The DCS system control room usually has an anti-static and moisture-proof floor of about 500mm, so the base height should be considered and its stability and strength should be guaranteed.

Grounding and installation of grounding system

DCS system has high requirements for grounding, which are generally divided into:

Intrinsically safe grounding

System DC working grounding

Protective grounding of AC power supply

Safety protection grounding, etc.

Various grounding systems and grounding busbars are insulated from each other.

Each grounding system can be connected to its own busbar and grounding electrode only after checking that there is no mixed line.

The system DC working grounding requirements are the highest, and different systems have different requirements. The resistance value generally cannot exceed 1Ω, so the grounding electrode must be installed.

The grounding requirements for other systems are that the grounding resistance is less than 4Ω.

The safety protection grounding can be connected to the ground network of the entire plant system.



Available every working day from 8:00AM to 8:00PM Contact us to place an enquiry

Email us

Reply within one working day

Visit us

32D Guomao Building, No.388, Hubin South Road, Siming District

Please read on, stay posted, subscribe, and we welcome you to tell us what you think.

submit
Contact Us
Location 32D Guomao Building, No.388, Hubin South Road, Siming District

Disclaimer : Salesplc sells new and surplus products and develops channels for purchasing such products. This website has not been approved or recognized by any of the listed manufacturers or trademarks. Salesplc is not an authorized distributor, dealer, or representative of the products displayed on this website. All product names, trademarks, brands, and logos used on this website are the property of their respective owners. The description, explanation, or sale of products with these names, trademarks, brands, and logos is for identification purposes only and is not intended to indicate any association with or authorization from any rights holder.



Copyright @2024 SalesPlc Limited. Sitemap / Blog / XML / Terms And Conditions / Privacy Policy Network Supported

vk YouTube Tiktok Pinterest Reddit teitter linkedin. facebook
leave a message
If you are interested in our products and want to know more details,please leave a message here,we will reply you as soon as we can.
submit

Home

Products

whatsApp

Contact Us

About Us

Salesplc has a team of experienced professionals working closely with overseas suppliers to provide our customers with a wide selection of products to meet their needs about delivery, price and brands . Salesplc advantage lies not only in our ability to provide products, but also in our ability to establish close links with direct users, system integrators and provide professional spare parts solutions to enhance customers' competitiveness in their own markets. Integrated procurement, online component solutions at any time, 24/7 and 365 days a year to place orders. To meet the specific needs of many manufacturing customers, we have deployed a range of supplies,With our multi-channel distribution network and strong warehouse support, we are able to optimize the supply chain and provide competitive prices. 20 years ago, we set sail with a dream,20 years later, we are shouldering more hopes and expectations. Thanks to every friend who supports us, it is your trust that keeps us moving forward. Looking back, we are grateful; looking forward to the future, we are full of confidence! Celebrate the 20th anniversary together and welcome a more brilliant tomorrow! We will continue to provide the best service and quality assurance to our customers all over the world in the coming days, welcome to inquire for the latest discount offer!     Our warehouse is capable of holding up to 60,000 pallet spare parts as a regional hub, enabling us to store a wide range of products. This improves efficiency by providing our customers in the global region with faster delivery times and lower prices. Sustainable Partnership   Salesplc is committed to building sustainable partnerships with customers and suppliers. It's a win-win-win situation. Sustainability also means responding to trends, evolution and innovation. This flexibility is also a guarantee of the future.We always focus on top brand products, top industrial partners innovation and industrial automation in the delivery of new components. Our sales office ensures that your to inquiries about spare parts are responsive. We actively participate in the customer's search for spare parts solutions or provide customized delivery advice. The customer's spare parts demand or delivery time question is always important to us.   + Availability, + Responsiveness: Your satisfaction is our top priority!   Salesplc spare parts supply chain ensures your optimization of the delivery cycle of industrial parts.

Where to Find Us

32D Guomao Building, No.388, Hubin South Road, Siming District +86-18030235312 sales8@askplc.com

Follow Us